Foster Hangar Foundation Excavations
Foundation excavations at the Lakeland Linder Regional Airport just prior to preparing the slab for a concrete pour. We anticipate starting to erect the hangar within the first week of December. Be sure to check our website next month for the finished concrete slab and the start of the building erection.
Foster Hangar Foundation Excavations Read More »
Barney’s Pump – Completed Project
This building is the future home of Unitron Controls, they build control panels for lift station pumps. Tucker team added 2,400 SF of manufacturing space to clients existing warehouse. We also renovated existing office with storage, reinforced existing metal building, installed 2 ton capacity crane rail system, paving, and increased electrical power to meet the Owners needs.
Barney’s Pump – Completed Project Read More »
Slab & Completed Trench Drain
At the Lakeland Linder Regional Airport, the slab has been poured and trench drain installed. We have started erecting the metal building and anticipate completion by the end of January. Please continue checking our website to view the completed metal building.
Slab & Completed Trench Drain Read More »
Dr. Siddiqui Office/ Lab- Progress December 2015
The outside of the building is almost complete. Sitework is done, landscaping is being installed and some painting needs to be completed.Inside the building a lot of things are taking place. Flooring is being installed, walls are painted, ceiling tiles are in, lights are on and the air is blowing. Carpenters are putting the finishing
Dr. Siddiqui Office/ Lab- Progress December 2015 Read More »
Foster Hangar Progress Update February 2016
We have finished sheeting the exterior walls and roof of the building, and are now installing the trim, gutters, and downspouts. Other current work includes installing the large exhaust fans and ductwork, new sprinkler system, Air Compressor, Water Evaporator and Sump Pump Systems. In roughly a week, the large exterior louvers will be getting installed
Foster Hangar Progress Update February 2016 Read More »